The Utility Regulator has granted NIE Networks an extension until 30 August 2022 to issue a connection offer for Cam Burn Windfarm.
Condition 30 of NIE Network’s Distribution Licence states that (barring specified exceptions) NIE Networks is obliged to make an offer for connection to the distribution system as soon as practicable and in any event within three months from receipt of a valid/completed application for connection.
The Utility Regulator has the powers to provide a consent for extensions to this time period under the same Condition.
Following review and full consideration of NIE Networks’ extension request regarding Cam Burn Windfarm, the Utility Regulator has provided consent to grant an extension to issuing an offer as soon as practicable but no later than 30 August 2022.
CAM Burn Extension Letter